Work is now under way on the first junction improvements as part of the A614/A6097 Major Road Network scheme, following the Mayor of the East Midlands’ efforts to secure approval and funding for the project.
The scheme, which will improve key junctions across Nottinghamshire, received a £12.6 million investment from Mayor Claire Ward after she successfully helped get the project over the line through direct engagement with Transport Secretary, Heidi Alexander, in September last year.
The work kicked off with targeted archaeology works on land off East Bridgford Road, Nottinghamshire, which will be followed by the construction of the site compound before main construction works begin in August.
This is one of five junctions being improved as part of the A614/A6097 scheme, including Ollerton Roundabout, which will help tackle congestion and make journeys quicker and easier at key pinch points in Lowdham, Ollerton, and Blidworth.

Mayor of the East Midlands Claire Ward said: “I know how much the A614/A6097 scheme matters to the people and businesses who rely on this route every day, whether they are navigating busy junctions such as Ollerton roundabout or travelling along the wider corridor. I recognise the real impact congestion, and delays have on everyday life.
“By prioritising £12.6 million of funding to support the full scheme it will deliver real benefits for people, helping them get to work, reach education, access services, and support local businesses.”
The major road improvements will focus on widening the junction to add an extra lane in each direction on the A6097 to increase capacity and reduce journey times. Right-turn lanes into Kirk Hill and East Bridgford Road will also be widened with new road markings aiming to make turning right safer and easier for motorists.
Junction improvements will also include a new traffic signal system to better manage vehicle flow, upgraded street lighting to increase visibility, the renewal of the footpath along Kirk Hill and upgrades to the bridleway crossing to improve access for pedestrians, cyclists and horse riders.

Councillor Mick Barton, Leader of Nottinghamshire County Council said: “This is a huge milestone, not only for the A614/A6097 scheme, but for Nottinghamshire as a whole.
“We know that residents and motorists have been waiting for many years to see improvements along the A614 and A6097 and we’re pleased that we’re now starting to make these junction improvements a reality.”
The Department for Transport have contributed a capped £24.3 million to the scheme, with an additional £8.3 million from Nottinghamshire County Council and £1.7m from developer contributions.
Works will begin at Kirk Hill in August, and motorists are advised to allow extra time when travelling in the area as a closure of Kirk Hill and East Bridgford Road will be in place for 12 months.
To find out more about the different phases of the construction and traffic management that will be in place, visit the county council’s website: www.nottinghamshire.gov.uk/a614